Construction of New Bridge 70m, 2 Span Pre-Stressed Box Girder Double Cell, Be'e Mos River Casnafar, Dare, Municipality of Dili
Ongoing
- Contract no.
- SSS/051/MOP-2023
- Contractor
- Carya Timor Leste Lda
- Contract value
- USD 3.632.896,18
- Sector
- Bridges
- Category
- Konstrusaun jerál
- Municipality
- Dili
- Funding source
- Fundu Infraestrutura (FI)
- Year
- 2023
- Start date
- 24 November 2023
- End date
- 24 November 2024
Data source: SIGP — Project Management Information System. Last updated: 9 October 2026