Skip to main content

Construction Of Retaining Wall for Slope Protection at Becora Au-hun to Bidau Sagrada Familia, Package I ( Sta, 3+300 - 3+700 ) Dili Municipality

Completed
Progress100%
Contract no.
ICB/122/MOP-2022
Contractor
Santana Diak Unipessoal Lda
Contract value
USD 1.330.780,92
Sector
Roads
Category
Konstrusaun jerál
Municipality
Dili
Owner
Direção Nacional de Construção de Vias Rodoviárias
Funding source
Fundu Infraestrutura (FI)
Year
2023
Start date
8 March 2023
End date
2 August 2024

Data source: SIGP — Project Management Information System. Last updated: 9 October 2026

Without coordinates

Community observations

Have you seen these works? Send an observation or photo about progress. MOP checks before publishing.