Consulting Services For the Feasibility Study / Detailed Design of Roads Manatuto - Natarbora ( 81 KMs ) and JCT. Laclubar - Laclubar ( 10 KMs ) and Construction Supervision of Roads Dili - Liquica ( 29 KMs ) and Tibar - Gleno ( 32 KMs )
Ongoing
- Contract no.
- TB-MPW001
- Contractor
- KATAHIRA & ENGINEERS INTERNATIONAL
- Contract value
- USD 9.507.634,63
- Sector
- Studies and design
- Category
- Konstrusaun jerál
- Funding source
- Fundu Infraestrutura (FI)
- Year
- 2012
- Start date
- 14 December 2012
- End date
- 16 December 2017
Data source: SIGP — Project Management Information System. Last updated: 9 October 2026