Obra Construcao de Recuperacao de Calamidade Moru Estrutura Protecao Ponte Loes, Pacote I (Sta. 0+080 to Sta. 0+200) Postu Adm. Maubara, Municipio Liquica

Ongoing
Contract no.
MPW-W-220252
Contractor
Centeliziumen Unip. Lda
Contract value
USD 563.751,66
Sector
Flood control
Category
Emerjénsia
Municipality
Liquiçá
Owner
Direcao Nacional de Prevencao e Controlo de Cheias
Funding source
Liña Ministeriál (LM)
Year
2022
Start date
29 November 2022
End date
29 April 2023

Data source: SIGP — Project Management Information System. Last updated: 9 October 2026