Obra konstrusaun ba moru protesaun, gabion no regularizasaun mota Sige Package II STA 0+360-STA 0+612.00

Ongoing
Progress87%
Contract no.
MPW-W-240130
Contractor
Sander Unipessoal Lda
Contract value
USD 365.784,30
Sector
Flood control
Category
Konstrusaun jerál
Municipality
Ainaro
Funding source
Liña Ministeriál (LM)
Year
2024
Start date
26 November 2024
End date
10 May 2025

Data source: SIGP — Project Management Information System. Last updated: 9 October 2026