Obra Konstrusaun ba Moru Protesaun Gabions ba Mota Sare Talimoro, Sta. 0+580 - 1+180 (Left Side), Suco Asulau Sare Talimoro, Posto Adm. Hatulia B, Municipio Ermera

Ongoing
Progress31%
Contract no.
MOP-EO-25027
Contractor
Blackbird, Unipessoal, Lda
Contract value
USD 235.136,21
Sector
Flood control
Category
Konstrusaun jerál
Municipality
Ermera
Owner
Direcao Nacional de Prevencao e Controlo de Cheias
Funding source
Liña Ministeriál (LM)
Year
2025
Start date
24 February 2025
End date
24 October 2025