Obra konstrusaun Moru Protesaun Cyclop & Groynes Mota Obrato, Municipio Manatuto, Package II Sta. 0+229 - Sta. 0+458, Suco Obrato, Posto Adm. Manatuto, Municipio Manatuto

Ongoing
Progress19%
Contract no.
MOP-EO-25057
Contractor
Joemajemel, Unipesoal,Lda
Contract value
USD 560.154,26
Sector
Flood control
Category
Konstrusaun jerál
Municipality
Manatuto
Owner
Direcao Nacional de Prevencao e Controlo de Cheias
Funding source
Liña Ministeriál (LM)
Year
2025
Start date
26 March 2025
End date
4 September 2025

Data source: SIGP — Project Management Information System. Last updated: 9 October 2026