Obra Konstrusaun Moru Protesaun Cyclope & Groynes Mota Obrato, Municipio Manatuto, Package VI Sta. 1+145 - Sta. 1+373, Suco Obrato, Posto Adm. Manatuto, Municipio Manatuto

Ongoing
Progress2%
Contract no.
MOP-EO-25052
Contractor
Nifra Marti, Unipesoal, Lda
Contract value
USD 558.219,20
Sector
Flood control
Category
Emerjénsia
Municipality
Manatuto, Manatuto
Owner
Direcao Nacional de Prevencao e Controlo de Cheias
Funding source
Liña Ministeriál (LM)
Year
2025
Start date
20 March 2025
End date
26 August 2025