Skip to main content

Obra Konstrusaun Moru Protesaun, Pakote II ba Mota Hera Hali Dolar, Gabion & Regularizasaun, Sta. 0+400 - 0+686, Aldeia Hali Dolar, Suco Hera, Posto Adm. Cristo Rei, Municipio Dili

Ongoing
Contract no.
MOP-EO-25070
Contractor
JHON TISIA, Unipessoal, Lda
Contract value
USD 269.623,31
Sector
Flood control
Category
Emerjénsia
Municipality
Dili, Cristo Rei, Culu Hun, Hali dolar
Owner
Direcao Nacional de Prevencao e Controlo de Cheias
Funding source
Liña Ministeriál (LM)
Year
2025
Start date
7 April 2025
End date
25 November 2025

Data source: SIGP — Project Management Information System. Last updated: 9 October 2026