Obra Rehabilitasaun Drainagen iha Area Fomento II (Externato), Left Side (Sta. 0+000 - 0+080 & Sta. 0+143.82 - 0+201), Right Side (Sta. 0+000 - 0+077.20 & Sta. 0+105.16 - 0+201), Aldeia Fomento II, Suco Comoro, Posto Adm. Dom Aleixo, Municipio Dili
Ongoing
- Contract no.
- MOP-EO-25079
- Contractor
- Blackbird, Unipessoal, Lda
- Contract value
- USD 45.380,29
- Sector
- Flood control
- Category
- Emerjénsia
- Municipality
- Dili, Dom Aleixo, Bebonuk, Fomento II
- Owner
- Direcao Nacional de Prevencao e Controlo de Cheias
- Funding source
- Liña Ministeriál (LM)
- Year
- 2025
- Start date
- 7 April 2025
- End date
- 2 September 2025
Data source: SIGP — Project Management Information System. Last updated: 9 October 2026
Without coordinates
Community observations
Have you seen these works? Send an observation or photo about progress. MOP checks before publishing.