Obra Rehabilitasaun Drainagen iha Area Fomento II (Externato), Left Side (Sta. 0+000 - 0+080 & Sta. 0+143.82 - 0+201), Right Side (Sta. 0+000 - 0+077.20 & Sta. 0+105.16 - 0+201), Aldeia Fomento II, Suco Comoro, Posto Adm. Dom Aleixo, Municipio Dili

Ongoing
Contract no.
MOP-EO-25079
Contractor
Blackbird, Unipessoal, Lda
Contract value
USD 45.380,29
Sector
Flood control
Category
Emerjénsia
Municipality
Dili, Dom Aleixo, Bebonuk, Fomento II
Owner
Direcao Nacional de Prevencao e Controlo de Cheias
Funding source
Liña Ministeriál (LM)
Year
2025
Start date
7 April 2025
End date
2 September 2025