Skip to main content

Project Supervision Consultant (PSC) of Power Distribution Modernization Project in Caicoli, Dili, Timor Leste

Ongoing
Contract no.
RFP/061/MOP-2022
Contractor
SMEC International Pty Ltd
Contract value
USD 2.892.140,00
Sector
Studies and design
Category
Konstrusaun jerál
Municipality
Dili
Funding source
Fundu Infraestrutura (FI)
Year
2023
Start date
6 June 2023
End date
6 September 2023