Rehabilitasaun Estrada Rural Poetete-Ermera Chainage 4+000-6+000, Package III Suco Poetete-Talimoro, Posto Adm. Gleno & Ermera, Municipio Ermera
Ongoing
Progress18%
- Contract no.
- MOP-EO-25081
- Contractor
- Peregrinhas, Unipessoal, Lda
- Contract value
- USD 344.230,60
- Sector
- Roads
- Category
- Roads for Development (R4D)
- Municipality
- Ermera, Ermera, Raimerhei
- Owner
- Direção Nacional de Construção de Vias Rodoviárias
- Funding source
- Liña Ministeriál (LM)
- Year
- 2025
- Start date
- 7 April 2025
- End date
- 7 April 2026
Data source: SIGP — Project Management Information System. Last updated: 9 October 2026
Without coordinates
Community observations
Have you seen these works? Send an observation or photo about progress. MOP checks before publishing.