Rehabilitasaun Estrada Rural,Molop Chainage, Bobonaro 0+000-2+000 (2.0 Km)
Ongoing
Progress79%
- Contract no.
- RT/048/MOP-2021
- Contractor
- Lombel Unipessoal, Lda
- Contract value
- USD 364.044,68
- Sector
- Roads
- Category
- Konstrusaun jerál
- Municipality
- Bobonaro
- Funding source
- Fundu Infraestrutura (FI)
- Year
- 2022
- Start date
- 8 March 2022
- End date
- 8 February 2023
Data source: SIGP — Project Management Information System. Last updated: 9 October 2026