Rehabilitasaun Estrada Rural,Taliforleu -kolohoho (Loop around Lake) Chainage, Aileu 2+000-5+000
Ongoing
Progress39%
- Contract no.
- RT/090/MOP-2021
- Contractor
- Saksaur Unipessoal, Lda
- Contract value
- USD 353.952,41
- Sector
- Roads
- Category
- Konstrusaun jerál
- Municipality
- Aileu
- Funding source
- Fundu Infraestrutura (FI)
- Year
- 2022
- Start date
- 28 April 2022
- End date
- 28 April 2023
Data source: SIGP — Project Management Information System. Last updated: 9 October 2026
Community observations
Have you seen these works? Send an observation or photo about progress. MOP checks before publishing.