Rehabilitation Estrada Rural Nabo-Daragata, STA 6+000 - 8+300 Suco Loiulu, Irabin de Cima, Bahatata, Posto Adm. Uatucarbau, Municipio Viqueque.
Ongoing
Progress10%
- Contract no.
- MPW-W-240119
- Contractor
- Bannila Unip. Lda; Zvanirabim Unip. Lda
- Contract value
- USD 438.816,67
- Sector
- Flood control
- Category
- Konstrusaun jerál
- Municipality
- Viqueque
- Owner
- Direcao Nacional de Prevencao e Controlo de Cheias
- Funding source
- Liña Ministeriál (LM)
- Year
- 2024
- Start date
- 30 November 2024
- End date
- 31 December 2025
Data source: SIGP — Project Management Information System. Last updated: 9 October 2026
Community observations
Have you seen these works? Send an observation or photo about progress. MOP checks before publishing.