Skip to main content

Rehabilitation Estrada Rural Nabo-Daragata, STA 6+000 - 8+300 Suco Loiulu, Irabin de Cima, Bahatata, Posto Adm. Uatucarbau, Municipio Viqueque.

Ongoing
Progress10%
Contract no.
MPW-W-240119
Contractor
Bannila Unip. Lda; Zvanirabim Unip. Lda
Contract value
USD 438.816,67
Sector
Flood control
Category
Konstrusaun jerál
Municipality
Viqueque
Owner
Direcao Nacional de Prevencao e Controlo de Cheias
Funding source
Liña Ministeriál (LM)
Year
2024
Start date
30 November 2024
End date
31 December 2025