Rehabilitation of Sarlala Road Protection Wall In Aileu Municipality
Ongoing
Progress78%
- Contract no.
- SSS/189/MOP-2024
- Contractor
- Sali Magu Unipessoal Lda
- Contract value
- USD 1.585.821,87
- Sector
- Flood control
- Category
- Konstrusaun jerál
- Municipality
- Aileu
- Funding source
- Fundu Infraestrutura (FI)
- Year
- 2024
- Start date
- 13 December 2024
- End date
- 13 June 2025