Rural Road Rehabilitation of the Rural Road Aituhun - Manufoni Chainage 0+000 - 1+000 ( 1.0 km ), Aileu Municipality
Completed
Progress98%
- Contract no.
- RT/088/MOP-2021
- Contractor
- Hatutan Moris Unipessoal Lda
- Contract value
- USD 98.575,19
- Sector
- Roads
- Category
- Konstrusaun jerál
- Municipality
- Aileu
- Funding source
- Fundu Infraestrutura (FI)
- Year
- 2022
- Start date
- 9 May 2022
- End date
- 9 May 2023
Data source: SIGP — Project Management Information System. Last updated: 9 October 2026
Community observations
Have you seen these works? Send an observation or photo about progress. MOP checks before publishing.