Upgrading and Maintenance of Baucau - Viqueque Highway Project Lot 2: Venilale - Viqueque : Sta. 27 + 120 to Sta. 62 + 010
Ongoing
Progress100%
- Contract no.
- ICB/046/MOPTC-2017
- Contractor
- China Railway Int. Group co.
- Contract value
- USD 23.853.175,70
- Sector
- Roads
- Category
- Konstrusaun jerál
- Municipality
- Viqueque
- Funding source
- Fundu Infraestrutura (FI)
- Year
- 2019
- Start date
- 21 March 2019
- End date
- 21 March 2022
Data source: SIGP — Project Management Information System. Last updated: 9 October 2026