Urgent Lo'omea River Protection Aligment III Down Right (Sta. 1+200-1+950
Ongoing
Progress80%
- Contract no.
- SSS/075/MOP-2024
- Contractor
- Super Jaya Unip.Lda
- Contract value
- USD 1.968.158,32
- Sector
- Flood control
- Category
- Konstrusaun jerál
- Municipality
- Covalima
- Funding source
- Fundu Infraestrutura (FI)
- Year
- 2024
- Start date
- 1 July 2024
- End date
- 1 July 2025
Data source: SIGP — Project Management Information System. Last updated: 9 October 2026