Urgent Lo'omea River Protection Alignment I Right (Sta. 0+000 - Sta. 1+176)

Ongoing
Progress50%
Contract no.
SSS/073/MOP-2024
Contractor
Montana Diak, Unipessoal, Lda
Contract value
USD 3.024.765,07
Sector
Flood control
Category
Konstrusaun jerál
Municipality
Covalima
Funding source
Fundu Infraestrutura (FI)
Year
2024
Start date
1 July 2024
End date
31 December 2024