- 60
- Projetos
- 52
- Em curso
- 8
- Concluídos
- USD 39.500.698
- Valor do contrato
Estado das estradas
Sem avisos ativos.
Projetos neste município
- New Installation MV Line, Transformer and LV Line New Distribution Line Sucu Katrai-Kraik Sucu Haupu District Ermera · Vandame Unip,Lda Concluídos
- New Installation MV, LV Line and House Connection from Letefoho to Cailiti, Rotuto, Kulau Haburas and Hathur Arbouthou - Ermera Municipality Edifícios públicos · Lecora Unip. Lda Concluídos
- New Installation MV, LV Line and House Connection from Hatulia to Bilimau, Tata and Titir Mata - Ermera Municipality Edifícios públicos · Hupai Construction Unip. Lda Concluídos
- New Installation MV, LV Line and House Connection from Mertutu to Mambata, Kailmate, Haturegas and Nilbroen - Ermera Municipality Edifícios públicos · Betulala Unip. Lda Concluídos
- New Installation MV,LV Line and House Connection from Malabe to Mota Taidasi,Atara mania and Atara Ermera District Controlo de cheias · Camlai Unip,Lda Concluídos
- Manutensaun Estrada Seksaun Humboe-Ermera Lama (Link A11-01 to Link C13), Sta 0+000 - Sta 4+920 & Mertuto - Villa Maria, Sta 0+000 - 4+690, Package 2 Estradas · Betuhei Unipessoal, Lda 100% Concluídos
- Emergency Project, Cyclone Seroja 04 Abril 2021 "Bilimau Bridge Spur or Groynes & Retaining Wall, Municipality of Ermera Controlo de cheias · Sali Magu Unipessoal Lda Concluídos
- Rehabilitation of Rural Road Lequimea Chainage 0+000 - 2+100 Ermera Municipality Estradas · Maluk Unip. Lda 100% Concluídos
- Rehabilitation Marobo - Hatolia Road Package 2 ( 05+200-10+000 km ) in Ermera District Estradas · FANEKI UNIPESSOAL, LDA 70% Em curso
- Design Review and Construction Supervision and Preparation of Bidding Documents for Upgrading and Maintenance of Jct. Letefoho Gleno Road Section (30+230-54+370 Km) - Section Estudos e projetos · Dasan Consultants Co.,Ltd (Republic of Korea) 0% Em curso
- Construction Supervision for Upgrading and Maintenance of Jct. Hatubelico to Letefoho Road Section (18,50 KM), Contract Package 2 (CP-2), (KM 11+900 to KM 30+307,88 Estudos e projetos · Kunhwa Engineering & Consulting Co., Ltd Em curso
- Rehabilitation of Ermera- Hatolia Roads Estradas · Suai Indah Unipessoal Lda Em curso