Skip to main content

Konstrusaun Rekuperasaun Box Culvert, " STA 0+000-0+015:"Retaining Wall (1-4), "STA 0+017, STA 0+000-0+013,STA 0+000-0+014 & SAT 0+000-0+008 Suai Holbelis, Suco Labarai, Posto Adm Suai, Municipio Covalima.

Ongoing
Progress100%
Contract no.
MPW-W-220267
Contractor
JUFADO, UNIPESSOAL, LDA
Contract value
USD 64.341,41
Sector
Flood control
Category
Emerjénsia
Municipality
Covalima
Owner
Direcao Nacional de Prevencao e Controlo de Cheias
Funding source
Liña Ministeriál (LM)
Year
2022
Start date
14 December 2022
End date
31 August 2024

Data source: SIGP — Project Management Information System. Last updated: 9 October 2026

Without coordinates

Community observations

Have you seen these works? Send an observation or photo about progress. MOP checks before publishing.