Manutensaun Rutina Estradas Rural: Fahisoi - Daillouta chainagea,0 - 5+000 km; Fahisoi Fadabloku Chainage 0+000 - 9+000 km; Fahisoi - Dailouta Chainage +000 - 5+000 km (R4D Manutensaun Rutina Estrada Rural: Fahisoi-Dairlouta Chainage 0+000 - 5+000, Fahisohi - Fadabloko Chainage 0+000 - 9+000, Hautoho-Liquica Chaiange 0+000 - 2+500, Municipio Aileu)
Ongoing
Progress84%
- Contract no.
- MOP/CB/NCB/200
- Contractor
- Bintang Fajar Unip.Lda
- Contract value
- USD 131.037,22
- Sector
- Roads
- Category
- Konstrusaun jerál
- Municipality
- Aileu
- Funding source
- Liña Ministeriál (LM)
- Year
- 2022
- Start date
- 23 September 2022
- End date
- 21 October 2023