Manutensaun Rutina Estradas Rural: Fahisoi - Daillouta chainagea,0 - 5+000 km; Fahisoi Fadabloku Chainage 0+000 - 9+000 km; Fahisoi - Dailouta Chainage +000 - 5+000 km (R4D Manutensaun Rutina Estrada Rural: Fahisoi-Dairlouta Chainage 0+000 - 5+000, Fahisohi - Fadabloko Chainage 0+000 - 9+000, Hautoho-Liquica Chaiange 0+000 - 2+500, Municipio Aileu)

Ongoing
Progress84%
Contract no.
MOP/CB/NCB/200
Contractor
Bintang Fajar Unip.Lda
Contract value
USD 131.037,22
Sector
Roads
Category
Konstrusaun jerál
Municipality
Aileu
Funding source
Liña Ministeriál (LM)
Year
2022
Start date
23 September 2022
End date
21 October 2023

Data source: SIGP — Project Management Information System. Last updated: 9 October 2026