Obra Konstrusaun Moru Protesaun, Gabion Mota Lotan (Package II Right Side, Sta. 0+000 - Sta. 0+500 ) Aldeia Lotan, Suco Batugede, Posto Adm. Balibo, Municipio Bobonaro

Ongoing
Contract no.
MPW-W-230125
Contractor
Ely Karya Unip. Lda
Contract value
USD 342.457,16
Sector
Flood control
Category
Konstrusaun jerál
Municipality
Bobonaro
Owner
Direcao Nacional de Prevencao e Controlo de Cheias
Funding source
Liña Ministeriál (LM)
Year
2023
Start date
27 November 2023
End date
30 April 2024